Delivery

Six gates, and then the clock starts.

Nothing ships until every one is answered. The lead-time clock runs from your signed readiness confirmation — because a purchase order does not make a site ready, and pretending otherwise is how delivery dates get missed.

#The gateWhat it means, and what it costs if it is wrong
1Dedicated RCD-protected 10A GPO at each pointClient-side lead item — allow about three weeks. The single most common cause of a delayed go-live.
2Site network or usable mobile coverageMarginal or absent coverage is not a decline; it becomes an offline-caching build, specified at scoping rather than discovered at commissioning. Points and handheld peripherals both hold a local copy and reconcile when the link returns.
3Not a classified hazardous areaNo acuitystore® equipment is Ex-rated. Zone 0, 1 or 2 is a decline, not a quote. We will not engineer around it.
4An item list in a workable digital formatWe handle the data quality. We cannot start without digital files.
5A product distributor or supplier in placeWe track and distribute items, we do not supply them — so the items, and the working capital behind them, need a supplier.
6A primary contact nominatedOne person who can answer a question the same day.
Environment

Where the standard specification stops.

ConditionStandardBeyond it
Ambient0–40°COPT-HAMB to +50°C — uncooled demountables, workshops, ROM areas
DustNormal industrialOPT-IP54 — crushing circuits, ROM areas, unsealed workshops
CorrosionNormal industrialOPT-MAR marine grade — port and offshore-adjacent
Hazardous areaNot ratedNothing. This is a decline.
Standard lead times

From a signed readiness confirmation.

ShapeWorking days
acuitystore® ONE — one Terminal or coil unit, from the finished-goods buffer20
acuitystore® CAMPAIGN — rented for the window, metro from stock10
Two to six points40
Seven to twelve points48
Regional · remote adders+5 · +10
Per inspection regime+3
And afterwards

Service that does not thin out at go-live.

EssentialOperateAssured
Applies to1–2 points3–12 points13+ points, or any life-safety gate
Severity-124×7×36524×7×36524×7×365
ContactPooled queue, portal firstNamed CSM, quarterlyNamed CSM, monthly

Severity-1 is on every tier, including the smallest. A life-safety gate — gas monitors, LOTO, competency-gated issue — forces Assured regardless of size, at no additional charge.

The next step

Work through the six gates before you order.

They are the whole readiness test, and they are the six things that decide whether a date can be held. If all six are clear, the standard lead time runs from the day you confirm it.